Lavon and Wallace Pump Stations

Industrial Services / Case Studies /

Lavon and Wallace Pump Stations

Garland, Texas

  • $6.03M reconstruction of 32 MGD and 28 MGD pump stations for the Garland Utility district
  • Excavation of over 22,000 CY of earth
  • Placement of 9,890 CY of concrete, tying the 42” line into an existing 5MM gallon storage tank
  • Installation of (9) 200-500 HP pumps
  • Installation of new SCADA system
  • Installation of new electrical transformers and switchgear
  • Repairs and upgrades to existing building systems.
 